Ask HN: Contractor payment issue

4 points by hector_ka ↗ HN
After I finished a 30 hour contract (I worked more like 50 hours on this)the guy keeps calling me to fix different issues but for free. How should I handle this?

8 comments

[ 3.4 ms ] story [ 31.1 ms ] thread
If they're actual bugs then you should fix them. If it's new features then explain that you'd need to allocate additional funds for additional work.
The guys seem to be clueless and they blame me for whatever issue comes up
How would you classify these things? Bugs that are resulting from "undocumented features"? Or is it PEBKAC and they're calling you to be personal tech support?

If it's 1 you can point to the spec, and if it's 2 you might have to sit down and explain why it's not your domain? Or if it is, how you would bill to fix it?

In either case I'm thinking this client fits in the "Thanks but no thanks" for future work.

Well the guy is asking me if an integer is 32 bits .
You have to draw a line. If he's changing what he meant or something was mis-interpreted that's not entirely your fault so it's not entirely your time for free.

When you launch something, give him 15-30 days to find anything, that's it. Anything after 15-30 days is billable.

Make sure you have every feature clearly defined before building things. Get signoff at every step of "What are we trying to build", "How are we going to build it" via email so there's no room for misinterpretation or misunderstanding.

Customers will always be clueless, thats why they hired you. Educating them on how software works, interacts and affects things takes time, unfortunately.

If he's calling you to fix something that you gave to him, that was broken because you messed up: -Fix it for free. You sold him a bill of goods, and it's your responsibility if it's broken. Broken does not include things like a new feature that they feel should have been part of the original spec, but never told you about. It also does not include changes in the design that they had already approved.

If he is calling you to add something (or change something) that he thought should have been part of the spec, but never actually told you about: -Charge if it's more than a few hours. Tons of clients sell a developer/designer on a spec, only to change their mind once it is all done. This is not your fault. Just because they don't like their idea once they see it, doesn't mean you should eat the cost.

All that being said, some clients (read: most clients) will always try to get some work done for free. If they are a good client, that has a proven track record of being understanding when you need more hours, or listen to your recommendations, then go ahead and do a few hours of free work to make them happy. But if this is your first project with this guy, you need to stand firm. Work is not free. New features are not free. Changes are not free. These are all things that take you away from the things you love in life, and you need to be compensated for. If they don't understand this, than they are free to search for someone who will work for free. My old coach (boxing) used to say, "Only a fool gets punched for free".

Don't let a client bully you into becoming a volunteer worker.

I should send this link to the client
What does the contract say? Does it say 30 hours, then you charge by the hour? Or a 30 hour flat fee and certain results?

You need to look up the term "change order" and start sending them.