I thought these two parts were the most interesting:
"A clue to the underlying problem with the planning algorithm was uncovered by Newby-Clark et. al. (2000), who found that:
Asking subjects for their predictions based on realistic "best guess" scenarios; or
Asking subjects for their hoped-for "best case" scenarios...
...produced indistinguishable results."
and:
"So there is a fairly reliable way to fix the planning fallacy, if you're doing something broadly similar to a reference class of previous projects. Just ask how long similar projects have taken in the past, without considering any of the special properties of this project. Better yet, ask an experienced outsider how long similar projects have taken."
I've been told a good rule of thumb for producing reasonable estimates is to make an estimate for how long you think it should take, then double the answer and add 10%. I never want to follow the advice when making estimates, as it feels like saying it'll take so much longer than I actually think it will might make it seem I'm inefficient, but in reality it turns out to be about right.
Perhaps also worth mentioning Hofstadter's Law:
"It always takes longer than you expect, even when you take Hofstadter's Law into account."
Double it is basically the engineering mantra -- The problem is when is occurs in big organisations and/or projects. The doubling can be compounded as the estimates trickle up.
I've seen reasonable estimates of 10d suddenly explode into 40+d once it makes it into upstream project plans.
Best thing to do is invest in metrics, and to revisit your estimates after the fact (nobody ever does this).
I've always gone with 4 times. That way even if it takes twice as long as I expected I still have plenty of time to either double check my work or goof off.
I've jokingly suggested for years that the right approach is to make your best estimate, then multiply by pi.
Not only does it boost the estimate enough that you're likely to hit the target, it also adds a lot of bogus precision to the numbers that the less-than-clueful will interpret as accuracy.
I've seen another formula around and it has worked well for me in the past. It was presented to me at a project management session. It's basically a weighted average:
(Best Case Scenario + Worst Case Scenario + (4 * Most Likely))/6
Whenever I come across articles discussing development estimation, I am reminded of the study discussed in Peopleware, the one in which the team that had no estimations finished first.
The only way to estimate (and I don't mean guess) that I have found to be reliable is the one mentioned in this article: to use previous data, and this only applies to the extent that what you're doing this time is very similar to what you did that time. Once you throw in any research, new technologies, new methodologies, that method is no longer applicable.
For this reason, I find value in separating Research (testing new methods, new technologies, integration methods) from Development (applying what you already know). Research is inestimable; as far as I am aware.
The thing with planning and estimation is that it's really the actual work in microcosm - you're building a model of what you want to do.
The tradeoff is - how much time do you want to spend on the model, instead of building it? You can get an absolute 100% accurate estimate if necessary - i.e. by doing the project and seeing how long it takes.
For tasks that are reasonably repetitive or normalised, this can be straightforward, and you can reuse old models. the problem is larger software projects (like a unique building) usually involves either (1) high levels of complexity, such as legacy data or large levels of integration or (2) a lot of otherwise novel aspects, such as a new bit of R&D.
But the errors aren't random; they are (experiment shows) overwhelmingly in the direction of optimism. How can it take lots and lots of expensive little detail work to correct such a gross statistical bias with a known direction?
This is the idea that underpins "poker planning" used in some agile software methodologies. You estimate a feature's required effort relative to other features that you (or the team) have completed in the past.
It's interesting to me, because I've always been more partial to Joel Spolsky's philosophy that only the developer who implements a feature can estimate it, and only after the feature has been designed in detail. This study says that is all wasted effort (it's the "inside view").
Very interesting. It happens that Pivotal Tracker https://www.pivotaltracker.com/, (full disclosure: from my employer Pivotal Labs), is built to combat this bias via the concept of "emergent iterations." You specify "points" for each fine-grained task, and tracker determines your velocity over time in dealing with these tasks, and predicts future progress.
Therefore, the question for the user is "what other tasks is this task like?" at which point tracker can be the external observer, noting how long those tasks actually take. Interesting stuff, so I wrote a short post on this: http://pivotallabs.com/users/woosley/blog/articles/724-pivot...
Besides all popular explanations of "failure to plan" (based on various cognitive biases and reasoning errors), there could be also another effect in play.
Even for somebody who could produce a perfect estimate, sometimes it can be more strategical to present more "optimistic" estimate to others.
Deliberate underestimation can be used to get approval for a project which otherwise wouldn't get through (if a more realistic but much larger estimation would be given).
This can be a way how to get sunk cost fallacy [1] work for you.
"It's easier to ask for forgiveness than it is to get permission".
If we look at those example "estimation failure" projects, it did actually work for them in the end. They were not canceled, additionally money was poured into them. Maybe if the initial estimate was a correct $102M (instead of massively underestimated $7M), Sydney wouldn't have its landmark at all.
Actually, such strategical underestimation can work as a motivational tool even for a single actor (with no external parties involved). What can be daunting under realistic assessment, could become more palatable when taken in smaller chunks.
12 comments
[ 2.8 ms ] story [ 41.6 ms ] thread"A clue to the underlying problem with the planning algorithm was uncovered by Newby-Clark et. al. (2000), who found that:
Asking subjects for their predictions based on realistic "best guess" scenarios; or
Asking subjects for their hoped-for "best case" scenarios...
...produced indistinguishable results."
and:
"So there is a fairly reliable way to fix the planning fallacy, if you're doing something broadly similar to a reference class of previous projects. Just ask how long similar projects have taken in the past, without considering any of the special properties of this project. Better yet, ask an experienced outsider how long similar projects have taken."
Perhaps also worth mentioning Hofstadter's Law:
"It always takes longer than you expect, even when you take Hofstadter's Law into account."
I've seen reasonable estimates of 10d suddenly explode into 40+d once it makes it into upstream project plans.
Best thing to do is invest in metrics, and to revisit your estimates after the fact (nobody ever does this).
Not only does it boost the estimate enough that you're likely to hit the target, it also adds a lot of bogus precision to the numbers that the less-than-clueful will interpret as accuracy.
(Best Case Scenario + Worst Case Scenario + (4 * Most Likely))/6
Book summary with a table of some data from Michael Lawrence and Ross Jeffery's 1985 study: http://javatroopers.com/Peopleware.html#Chapter_5
The only way to estimate (and I don't mean guess) that I have found to be reliable is the one mentioned in this article: to use previous data, and this only applies to the extent that what you're doing this time is very similar to what you did that time. Once you throw in any research, new technologies, new methodologies, that method is no longer applicable.
For this reason, I find value in separating Research (testing new methods, new technologies, integration methods) from Development (applying what you already know). Research is inestimable; as far as I am aware.
The tradeoff is - how much time do you want to spend on the model, instead of building it? You can get an absolute 100% accurate estimate if necessary - i.e. by doing the project and seeing how long it takes.
For tasks that are reasonably repetitive or normalised, this can be straightforward, and you can reuse old models. the problem is larger software projects (like a unique building) usually involves either (1) high levels of complexity, such as legacy data or large levels of integration or (2) a lot of otherwise novel aspects, such as a new bit of R&D.
It's interesting to me, because I've always been more partial to Joel Spolsky's philosophy that only the developer who implements a feature can estimate it, and only after the feature has been designed in detail. This study says that is all wasted effort (it's the "inside view").
Therefore, the question for the user is "what other tasks is this task like?" at which point tracker can be the external observer, noting how long those tasks actually take. Interesting stuff, so I wrote a short post on this: http://pivotallabs.com/users/woosley/blog/articles/724-pivot...
Even for somebody who could produce a perfect estimate, sometimes it can be more strategical to present more "optimistic" estimate to others.
Deliberate underestimation can be used to get approval for a project which otherwise wouldn't get through (if a more realistic but much larger estimation would be given).
This can be a way how to get sunk cost fallacy [1] work for you.
"It's easier to ask for forgiveness than it is to get permission".
If we look at those example "estimation failure" projects, it did actually work for them in the end. They were not canceled, additionally money was poured into them. Maybe if the initial estimate was a correct $102M (instead of massively underestimated $7M), Sydney wouldn't have its landmark at all.
Actually, such strategical underestimation can work as a motivational tool even for a single actor (with no external parties involved). What can be daunting under realistic assessment, could become more palatable when taken in smaller chunks.