February 2019 --> no design freeze, 3 to 4 months to source components and make tooling (very optimistic). May/July 2019 --> start of production. June/August 2019 --> debug, SOP, build stock, start shipping Optimistic.…
Q3 is in my opinion too optimistic. Based on the status of hardware (TBD) there is probably no chance to start shipping parts in Q3. The design should be locked today. Will they be able to source the tools, get reliable…
February 2019 --> no design freeze, 3 to 4 months to source components and make tooling (very optimistic). May/July 2019 --> start of production. June/August 2019 --> debug, SOP, build stock, start shipping Optimistic.…
Q3 is in my opinion too optimistic. Based on the status of hardware (TBD) there is probably no chance to start shipping parts in Q3. The design should be locked today. Will they be able to source the tools, get reliable…